Location of performance / Site: | Ennigerloh, North Rhine-Westphalia, Germany, Europe |
---|---|
Period: | Jul 2003 - Jun 2006 |
Construction design for section I of the final capping system with three system alternatives and of a passive degasification in adjacent the area of the municipal solid waste landfill at the site "Ennigerlohn", including Health and Safety Plan, Ouality Assurance Plan.